Road No | Location | Description | Likely Duration (Days) | Remarks / Contacts |
---|---|---|---|---|
A4063 | Maesteg Road, Cymer and Glyncorrwg, Cymmer | Civils | 10-JUN-24 to 10-JUN-24 1 days | Temporary 2 way traffic 1 day only |
A4067 | Gwyn's Drift, Footbridge (Tesco), Alltwen, Pontardawe | Bridge Cleaning | 20-MAY-24 to 27-MAY-24 8 days | Multi Phase Traffic Light 24 hours Night time working |
A4107 | PENTWYN ROAD, EAST OF TRAVANCORE, CYNONVILLE, NEATH | FRAME AND COVER IN FOOTWAY | 04-JUN-24 to 04-JUN-24 1 days | Temporary 2 way traffic 1 day only |
A4107 | Station Road / Jct Lane Between Station Road / School Rd, Cymmer | Retaining Wall Construction and Closure of Lane | 26-FEB-24 to 30-JUN-24 126 days | Temporary Multi Phase Traffic Lights 24hrs |
A4109 | A4109 FROM CRYNANT TO SEVEN SISTERS, 132 DULAIS ROAD NEATH | POLE TESTING | 04-JUN-24 to 04-JUN-24 1 days | Temporary 2 way traffic 1 day only |
A4109 | HEOL Y GLYN, OUTSIDE , GLYN NEDD, NEATH | POLE IN VERGE | 24-MAY-24 to 24-MAY-24 1 days | Temporary 2 way traffic 1 day only |
A4109 | INTER VALLEY ROAD 50M NORTH OF TO CEFN UCHAF, GLYNNEATH | RENEW POLE IN VERGE | 02-JUL-24 to 02-JUL-24 1 days | Temporary 2 way traffic 1 day only |
A4109 | NEW ROAD, 20 YNYSYGERWN CRESCENT, ABERDULAIS | POLE BEND | 29-MAY-24 to 31-MAY-24 3 days | Multi Phase Traffic Light 24 hours |
A4221 | A4221 FROM DYFFRYN CELLWEN TO COUNTY BOUNDARY, APPROX 200M FROM THE JUNCTION OF A4109 TO A4221 LINK ROAD ON, ONLLWYN, | New Duct in the Verge | 15-MAY-24 to 17-MAY-24 3 days | Temporary 2 Way Traffic Control 24 hrs |
A4230 | NEW ROAD, OUTSIDE 95-97, SKEWEN | RENEW/REPAIR FRAME AND COVER | 04-JUL-24 to 06-JUL-24 3 days | Temporary 2 Way Traffic Control 24 hrs |
A474 | PONTARDAWE ROAD, APPROX 142M SOUTH OF ACCESS ROAD TOWARDS GARTH, RHYDYFRO, PONTARDAWE | FRAME AND COVER | 06-JUL-24 to 07-JUL-24 2 days | Temporary 2 Way Traffic Control 24 hrs |
A48 | Margam to Pyle road Margam | TM to control traffic entering and exiting the forthcoming "In It together festival" | 27-APR-24 to 23-MAY-24 27 days | Temporary Traffic Signals numerous location along A48 |
B4283 | Water St by Afan Landscapes, Margam | Drainage Improvements | 15-MAR-24 to 14-JUN-24 92 days | Temporary 2 Way Traffic Control 24 hrs (Coring Highways) |
B4283 | Water Street/Junction A48 Margam | Traffic management to control traffic for the forthcoming "In it Together Festival | 23-MAY-24 to 27-MAY-24 5 days | Multi Phase Traffic Light 24 hours Numerous location along Water Street |
B4286 | CWMAVON ROAD CWAMVON | Landslide | 26-JAN-23 to 31-AUG-24 584 days | Temporary 2 Way Traffic Control 24 hrs |
B4287 | Main Road O/S 5, Bevans Terrace, Pontrhydyfen | Reconstruction of highway at area of edge failure | 02-APR-24 to 25-JUN-24 85 days | Temporary 2 Way Traffic Control 24 hrs |
B4287 | Queen Street, Pelenna, Pontrhydyfen, | Tree Repairs | 16-MAY-24 to 16-MAY-24 1 days | Temporary 2 way traffic 1 day only |
B4434 | NEATH ROAD, TY GWYN, RESOLVEN | NEW SERVICE | 16-MAY-24 to 20-MAY-24 5 days | Temporary 2 Way Traffic Control 24 hrs |
B4434 | TAN Y RHIW, SIDE OF 2 RAILWAY TERRACE, RESOLVEN | CAMERA SURVEY | 24-JUN-24 to 28-JUN-24 5 days | Multi Phase Traffic Light 24 hours |
B4603 | Brecon Road, Pontardawe, Ynysmeudwy | Civils works | 24-JUN-24 to 24-JUN-24 1 days | Multi Phase Lights 1 day only (Core Highways) |
B4603 | HIGH STREET, OPPOSITE JUNCTION WITH DYNEVOR TERRACE, PONTARDAWE | FRAME AND COVER | 05-JUL-24 to 07-JUL-24 3 days | Temporary 2 Way Traffic Control 24 hrs |
B4603 | New Road, Pontardawe, Ynysmeudwy | Civils | 20-MAY-24 to 22-MAY-24 3 days | Temporary 2 Way Traffic Control 24 hrs |
B4603 | SWANSEA ROAD, TREBANOS, PONTARDAWE | repair cables | 15-MAY-24 to 15-MAY-24 1 days | Temporary 2 way traffic 1 day only |
U/C | ALLOY INDUSTRIAL ESTATE, Opposite Factory, TAWE TERRACE PONTARDAWE | Renew joint box cover footway | 03-JUN-24 to 03-JUN-24 1 days | Multi Phase Lights 1 day only |
U/C | ALLTYWERIN, Outside 86/88, PONTARDAWE | duct footway | 22-MAY-24 to 24-MAY-24 3 days | Temporary 2 Way Traffic Control 24 hrs |
U/C | BAGLAN WAY, OPP CRICKET GROUND. BAGLAN MOORS ABERAVON | NEW SUPPLY TO GLASS BUILDING DEVELOPMENT | 07-MAY-24 to 07-JUN-24 32 days | Temporary 2 Way Traffic Control 24 hrs LL0102413311 |
U/C | BRECON ROAD, JUNCTION OF COEDCAE , PONTARDAWE | FRAME AND COVER | 23-JUN-24 to 24-JUN-24 2 days | Multi Phase Traffic Light 24 hours |
U/C | Cronin Avenue, Sandfields East, Port Talbot | Poling | 21-MAY-24 to 21-MAY-24 1 days | Multi Phase Lights 1 day only |
U/C | DWR Y FELIN ROAD, Neath | NEW SERVICE CONNECTION | 23-JUN-24 to 25-JUN-24 3 days | |
U/C | ELFED AVENUE, CRONIN AVENUE, SANDFIELDS, PORT TALBOT | TM PURPOSES ONLY | 21-MAY-24 to 21-MAY-24 1 days | Multi Phase Lights 1 day only |
U/C | HEOL LLWYNON, OUTSIDE 9, HEOL CATWG, BRYNCOCH | REPLACE POLE | 22-MAY-24 to 22-MAY-24 1 days | Multi Phase Lights 1 day only |
U/C | HIGH STREET, JUNCTION OF GEORGE STREET, PONTARDAWE | FRAME AND COVER | 24-MAY-24 to 24-MAY-24 1 days | Multi Phase Lights 1 day only |
U/C | Llwyn Road, 98 Cwmgors, Neath | 17-MAY-24 to 17-MAY-24 1 days | ROAD CLOSED - Diversion in operation | |
U/C | MAESTEG ROAD, OUTSIDE 20, CYMMER | FRAME AND COVER | 01-JUL-24 to 02-JUL-24 2 days | Temporary 2 Way Traffic Control 24 hrs |
U/C | MOOR ROAD OUTSIDE NEW GLASS BUILDING DEVELOPMENT BAGLAN MOORS | S278 WORKS | 02-APR-24 to 17-MAY-24 46 days | Temporary 2 Way Traffic Control 24 hrs |
U/C | Old Road O/S 257, TYLA ROAD Neath | Relay gas service | 28-MAY-24 to 31-MAY-24 4 days | Multi Phase Traffic Light 24 hours |
U/C | Old Road Pontardawe, Ynysmeudwy | CIVILS | 20-MAY-24 to 22-MAY-24 3 days | ROAD CLOSED - Diversion in operation |
U/C | Pentwyn Road, 1 junction of Tan Y Rhiw Road, Resolven | Disconnect service at ferrule | 09-MAY-24 to 15-MAY-24 7 days | ROAD CLOSED - Diversion in operation contractors will allow access for local residents when required. |
U/C | Rugby Avenue, Lane Rear of 1-29, Neath | Renovation Works | 03-JUN-24 to 17-JAN-25 229 days | ROAD CLOSED - Diversion in operation |
U/C | WERN ROAD, OUTSIDE 79 - 80, SKEWEN | FRAME AND COVER | 28-MAY-24 to 30-MAY-24 3 days | Temporary 2 Way Traffic Control 24 hrs |