Road Works and Road Closures

Please see Traffic Wales for Motorway and Trunk roads roadwork information.

Local Road Works
Road No Location Description Likely Duration (Days) Remarks / Contacts
A4068 Gwilym Road Jct Lewis Avenue s/o 65 Gwilym Road, Cwmllynfell Renew Box Defect 15-OCT-24 to 15-OCT-24 1 days Multi Phase Lights 1 day only
A4107 Bulch Mountain Road, 600m east of 40 High Street, Abergwynfi Drainage Works 21-SEP-24 to 31-OCT-24 41 days Multi Phase Traffic Light 24 hours
A4107 Pentwyn Road, Cynonville Culvert, East of Property "Taverncore" Cynonville Retaining wall maintenance construction works 07-OCT-24 to 29-NOV-24 54 days Temporary 2 Way Traffic Control 24 hrs Carl Price Engineering's scheme 07956 221734
A4107 Bwlch Mountains Road, 340m east of 40 High Street, Abergwynfi Engineering works to the adjacent Coal tip 14-AUG-24 to 18-OCT-24 66 days Temporary 2 Way Traffic Control 24 hrs
A4109 Dulais Road, o/s 53 Seven Sisters Frame & Cover 10-OCT-24 to 14-OCT-24 5 days Multi Phase Traffic Light 24 hours
A4230 New Road Skewen Gas Mains Replacement 01-OCT-24 to 21-NOV-24 52 days Temporary 2 Way Traffic Control 24 hrs (Coring Highways)
A4230 New Road, o/s 95-97 Skewen Frame & Cover 27-OCT-24 to 27-OCT-24 1 days Temporary 2 way traffic 1 day only
A4230 Park Avenue, Opp 42, Lonlas, Neath Light Cable 11-OCT-24 to 15-OCT-24 5 days Temporary 2 Way Traffic Control 24 hrs
A4230 St Johns Terrace, Adj to Wesley Court, New Road, Neath Abbey Stop Tap 14-OCT-24 to 16-OCT-24 3 days Multi Phase Traffic Light 24 hours
A474 Briton Ferry Road, Cimla, Frame & Cover 20-OCT-24 to 20-OCT-24 1 days Multi Phase Lights 1 day only
A474 Commercial Road / Junction Pontardawe Road Pontardawe Drainage works 08-OCT-24 to 30-NOV-24 54 days Temporary 2 Way Traffic Control 24 hrs
A474 Commercial Road, Rhydyfro Pontardawe Sign Defect 22-OCT-24 to 22-OCT-24 1 days Temporary 2 way traffic 1 day only
A474 Commercial Road, Opp 87 Rhydyfro Pontardawe Renew frame and Cover 18-OCT-24 to 22-OCT-24 5 days Temporary 2 Way Traffic Control 24 hrs
A474 Delffordd 17-22, Adj to No 79 Neath Road Rhos, Pontardawe Gas Mains 14-OCT-24 to 08-NOV-24 26 days Temporary 2 Way Traffic Control 24 hrs (Coring Highways)
A474 Neath Abbey Rd, Neath Frame & Cover 10-NOV-24 to 10-NOV-24 1 days Multi Phase Lights 1 day only
A474 Neath Road, 200, Briton Ferry Remedial works 0930hrs to 1500hrs 10-OCT-24 to 14-OCT-24 5 days Temporary 2 Way Traffic Control 24 hrs
A474 Neath Road, Jct Plas Road Pontardawe Gas Mains 08-OCT-24 to 21-OCT-24 14 days Multi Phase Traffic Light 24 hours
A48 Wharf Road, Near the refuge Centre, Briton Ferry Testing / Investigation works to underside of A48 Structure 24-SEP-24 to 17-OCT-24 24 days Temporary 2 Way Traffic Control 24 hrs
B4286 Cwmavon Road Cwmavon Landslide 26-JAN-23 to 31-JAN-25 737 days Temporary 2 Way Traffic Control 24 hrs
B4286 Salem Road, Jct Depot Road, o/s Library Cwmavon New Mains 02-OCT-24 to 18-OCT-24 17 days Temporary 2 Way Traffic Control 24 hrs (Coring Highways)
B4290 Pen yr Heol, Skewen Network Rail Structural examination to steel on underside of bridge 02-JUL-24 to 22-NOV-24 144 days Temporary 2 Way Traffic Control 24 hrs
B4434 Neath Road Adj to 100 Resolven Excavation works 08-OCT-24 to 15-OCT-24 8 days Temporary 2 Way Traffic Control 24 hrs
B4434 Neath Road, Adj to 100 Resolven New Service 16-OCT-24 to 18-OCT-24 3 days Temporary 2 Way Traffic Control 24 hrs
B4434 New road, Nr entrance of Noddffa Bungalow Clyne Underground and overhead Cables 16-OCT-24 to 18-OCT-24 3 days Temporary 2 Way Traffic Control 24 hrs
U/C Church Street, from the junction of Railway Terrace Briton Ferry Maintenance works 02-NOV-24 to 03-NOV-24 2 days ROAD CLOSED - Diversion in operation
U/C Cyfyng Road o/s 20 & 41 Ystalyfera hoist 03-OCT-24 to 17-OCT-24 15 days Temporary 2 Way Traffic Control 24 hrs
U/C Lane Rear of 1-29 Rugby Avenue, Neath Renovation Works and Rendering of side elevation to properties 03-JUN-24 to 17-JAN-25 229 days ROAD CLOSED - Diversion in operation
U/C Lane off Maesteg Road, Cymmer Bore Holes 06-OCT-24 to 13-OCT-24 8 days ROAD CLOSED - Diversion in operation
U/C Maesteg Road, Station Road Cymmer Bore Holes 14-OCT-24 to 18-OCT-24 5 days Multi Phase Traffic Light 24 hours
U/C March Hywel Jct Plas Road Rhos Pontardawe Gas Mains 20-SEP-24 to 18-OCT-24 29 days Temporary 2 Way Traffic Control 24 hrs (Coring Highways)
U/C Mount View Terrace, Aberavon (Boundary Fence Network Rail) Clear vegetation from boundary fence 13-NOV-24 to 15-NOV-24 3 days ROAD CLOSED - Diversion in operation 08:30 - 15:00
U/C Old Road, 126 Neath Renew Service 14-OCT-24 to 16-OCT-24 3 days Temporary 2 Way Traffic Control 24 hrs
U/C Regent Street West, Briton Ferry Repairs to Underside Bridge 11-NOV-24 to 22-NOV-24 12 days ROAD CLOSED - Diversion in operation
U/C Tonmawr Road Nr Forest Lodge Tonmawr Drainage works 15-JUL-24 to 14-OCT-24 92 days Temporary 2 Way Traffic Control 24 hrs (Coring Highways) Steve Jones
U/C Beechwood Avenue, Neath Gas Mains replacement works 04-SEP-24 to 18-OCT-24 45 days Multi Phase Traffic Light 24 hours (coring Highways)