Road No Location Description Likely Duration (Days) Remarks / Contacts
A4063 Maesteg Rd Lane to Red Field to the Junction of Eastern Avenue Maesteg Road, Cymmer Bank Stabilisation and Post and Rail remedial works 04-NOV-24 to 31-JAN-25 89 days Temporary 2 Way Traffic Control 24 hrs (Coring Highways)
A4107 Pentwyn Road, Cynonville Culvert, East of Property "Taverncore" Cynonville Retaining wall maintenance construction works 07-OCT-24 to 29-NOV-24 54 days Temporary 2 Way Traffic Control 24 hrs Carl Price Engineering's scheme 07956 221734
A4109 New Road, Nr Gas Gov Tonna New Pole Test 04-DEC-24 to 04-DEC-24 1 days Temporary 2 way traffic 1 day only
A4109 New Road, Nr Gas Gov, Tonna Aberdulais Pole Testing 04-DEC-24 to 04-DEC-24 1 days Temporary 2 way traffic 1 day only
A4241 Afan Way, on Roundabout near Jct with Harbour Way Aberavon HV Cable 28-NOV-24 to 30-NOV-24 3 days Lane Closures
A474 Commercial Road / Junction Pontardawe Road Pontardawe Drainage works 08-OCT-24 to 30-NOV-24 54 days Temporary 2 Way Traffic Control 24 hrs
A474 Dwr Y Felin Rd, Neath Abbey Rd, Roman Way, Neath Frame & Cover 01-DEC-24 to 01-DEC-24 1 days Multi Phase Lights 1 day only
A474 Heol Y Gors, O/S 244 Cwmgors Frame & Cover 03-DEC-24 to 03-DEC-24 1 days Temporary 2 way traffic 1 day only
A474 Neath Abbey Road, Neath Abbey Neath Tree Cutting 16-DEC-24 to 18-DEC-24 3 days Multi Phase Traffic Light 24 hours
A474 Neath Road, Jct Plas Road Pontardawe Gas Mains 08-OCT-24 to 29-NOV-24 53 days Multi Phase Traffic Light 24 hours
A474 Perthgwynion Access Road, to Pontardawe Road, Pontardawe Drainage Improvements 02-DEC-24 to 06-DEC-24 5 days Temporary 2 Way Traffic Control 24 hrs (Coring Highways)
A48 PENTYLA BAGLAN RD, O/S 69, ABERAVON maintenances works 28-NOV-24 to 28-NOV-24 1 days ROAD CLOSED - Diversion in operation
A48 Wellfield Road, o/s 9, Pentyla Baglan Road o/s Flats 1-12, Baglan Neath New Service 25-NOV-24 to 28-NOV-24 4 days Multi Phase Traffic Light 24 hours
A48 Wharf Road, Briton Ferry Neath Investigations 28-NOV-24 to 28-NOV-24 1 days Temporary 2 way traffic 1 day only
B4242 Neath Rd, opp Rear of 25 Edwards Terrace Abergarwed Emergency Asset 26-NOV-24 to 29-NOV-24 4 days Temporary 2 Way Traffic Control 24 hrs
B4286 Cwmavon Road Cwmavon Landslide 26-JAN-23 to 31-JAN-25 737 days Temporary 2 Way Traffic Control 24 hrs
B4287 Cimla Road, Rugby Avenue & Ena Avenue Neath mains Replacement 27-DEC-24 to 06-JAN-25 11 days ROAD CLOSED - Diversion in operation
B4287 MAIN ROAD PONTRHYDYFEN New pole 12-DEC-24 to 12-DEC-24 1 days Multi Phase Lights 1 day only
B4290 Ashleigh Terrace, to A483 Near Marshalling Yard, Jersey Marine Neath Maintenance work 02-DEC-24 to 02-DEC-24 1 days Temporary 2 way traffic 1 day only
B4290 Old Road, O/S 108, Compton Road Skewen Link Box 04-DEC-24 to 09-DEC-24 6 days Multi Phase Traffic Light 24 hours
B4290 Pen yr Heol, Skewen Network Rail Structural examination to steel on underside of bridge 02-JUL-24 to 31-MAR-25 273 days Temporary 2 Way Traffic Control 24 hrs
B4603 Brecon Road, Opp 80 Pontardawe Leak 27-NOV-24 to 30-NOV-24 4 days Temporary 2 Way Traffic Control 24 hrs
U/C Coed Du Road, Crynant New Service 06-JAN-25 to 08-JAN-25 3 days ROAD CLOSED - Diversion in operation
U/C Darwin Road, O/S 19 , Sandfields Frame & Cover 02-DEC-24 to 02-DEC-24 1 days Multi Phase Lights 1 day only
U/C Drummau Road Skewen Mains Replacement 25-NOV-24 to 06-DEC-24 12 days Temporary 2 Way Traffic Control 24 hrs (Coring Highways)
U/C Ffordd Cwm Tawe, Ystalyfera, Tree Cutting 04-DEC-24 to 06-DEC-24 3 days Temporary 2 Way Traffic Control 24 hrs
U/C Glyncorrwg Farm, Cymer Road, Glyncorrwg Drainage works 18-NOV-24 to 30-DEC-24 43 days Temporary 2 Way Traffic Control 24 hrs (Coring Highways)
U/C Graig Road, Nr 7 Dynevor Place Skewen Blockages 10-DEC-24 to 12-DEC-24 3 days ROAD CLOSED - Diversion in operation
U/C Heol Glynderwen 2 - 20, Waunceirch Neath Drainage Improvements 11-NOV-24 to 29-NOV-24 19 days Temporary 2 Way Traffic Control 24 hrs
U/C Lane Rear of 1-29 Rugby Avenue, Neath Renovation Works and Rendering of side elevation to properties 03-JUN-24 to 17-JAN-25 229 days ROAD CLOSED - Diversion in operation
U/C Lewis Road, 96-114 Neath Drainage Improvements 20-NOV-24 to 04-DEC-24 15 days Temporary 2 Way Traffic Control 24 hrs (Coring Highways)
U/C Maes YR Haf Road, Sub Station Neath Sub Station Works 25-NOV-24 to 29-NOV-24 5 days ROAD CLOSED - Diversion in operation
U/C Regent Street West, Briton Ferry Repairs to Underside Bridge 11-NOV-24 to 29-NOV-24 19 days ROAD CLOSED - Diversion in operation
U/C Wern Road, o/s 81 Skewen Joint hole 10-DEC-24 to 13-DEC-24 4 days Temporary 2 Way Traffic Control 24 hrs